    ESTUDIO DEL SCHEDULE CONTROL INDEX PARA EL CONTROL INTEGRADO DE PLAZO EN PROYECTOS

    Thumbnail
    Ver/
    CIIP10_0024_0033.PDF (89.16Kb)
    Fecha
    2010
    Autor
    Fernando Acebes, Adolfo
    López-Paredes, Javier Pajares
    Metadatos
    Mostrar el registro completo del ítem
    Resumen
    In this paper, we extend the cost-schedule monitoring methodologies in order to integrate project risk and variability. First, we define a “risk baseline” as the evolution of the project remaining risk over its project life cycle. Then, we define control indexes that are use together with the performance indexes defined under the monitoring system framework. These indexes allow project managers to detect whether the project overruns exceed the project “normal variability”, computed from the estimated variability of its individual activities. We also propose a graphical control system to monitor the variability buffer the project manager can use without endangering the project success. Keywords: cost-schedule control systems; project risk management; integrated project monitoring
    URI
    http://dspace.aeipro.com/xmlui/handle/123456789/2229
    Colecciones
    • CIDIP 2010 (Madrid) [239]

    DSpace software copyright © 2002-2016  AEIPRO
    Contacto | Sugerencias
     

     

    Listar

    Todo AEIPROComunidades & ColeccionesPor fecha de publicaciónAutoresTítulosMateriasEsta colecciónPor fecha de publicaciónAutoresTítulosMaterias

    Mi cuenta

    Acceder

    DSpace software copyright © 2002-2016  AEIPRO
    Contacto | Sugerencias